How it all links

From the site to payment without retyping. The site diary and the measurements make the claim, the claim gets its payment schedule, the schedule leads to payment and retention, and all of it feeds the registers and the reports. One project file carries it from tool to tool, and every record has an ID.

On your device only. Information, not legal advice.The tools run in your browser. The project file is saved where you choose and loaded when you choose: nothing you type is sent to us or stored, and there are no cookies.
How the free tools link: site diary and measurement, payment claim, payment schedule, payment and retention, registers and reports, joined by the project fileBEFORE THE PROJECTTender tracker →A won tender becomes the project, with its itemsBuild your project →Pick roles and tools: a starter file and workbook1Site diary andmeasurementProgress sheet →Site manager, foremanProject and site engineersEstimator: the items2PaymentclaimClaim builder →Quantity surveyorSubcontractorsDesign consultants3PaymentscheduleSchedule builder →Project managerContract administratorEngineer to the contract4Payment andretentionRetention calculator →Accounts payable, receivableCommercial managerClient's representative5Registers andreportsReports →Cost controller, plannerDocument controllerProcurementProject file: items, measurements, diary, claims, schedules, payments, retention, variations, RFIs, orders, transmittalsREPORTSDailySite daily reportWeeklyProgress reportCommercial reportMonthlyClaim substantiation, cost,claims and retention, procurement,client summaryEvery row of every report starts with the ID of the record it came from, and every report ends with its gaps. How the free tools link: site diary and measurement, payment claim, payment schedule, payment and retention, registers and reports, joined by the project fileBEFORE THE PROJECTTender tracker →A won tender becomes the project, with its itemsBuild your project →Pick roles and tools: a starter file and workbook1Site diary andmeasurementProgress sheet →Site manager, foreman · Project and site engineersEstimator: the items2PaymentclaimClaim builder →Quantity surveyor · SubcontractorsDesign consultants3PaymentscheduleSchedule builder →Project manager · Contract administratorEngineer to the contract4Payment andretentionRetention calculator →Accounts payable, receivable · Commercial managerClient's representative5Registers andreportsReports →Cost controller, planner · Document controllerProcurementProject file, every record with an ID:items, measurements, diary, claims,schedules, payments, retention, and moreREPORTSDailySite daily reportWeeklyProgress reportCommercial reportMonthlyClaim substantiation, cost,claims and retention, procurement,client summary
Each box opens its tool. The roles under each step are the people who usually work there. The project file joins them, and the reports read from it.

Before the project

Step by step

  1. Site diary and measurement

    The site manager or foreman keeps the diary: labour, plant, work done by item, delays, instructions, visitors, photos. Engineers measure each item and name the diary entry behind it. Progress sheet · Diary

  2. The claim

    The progress sheet turns the measurements into claim lines, each with its item and measurement IDs. The claim builder makes the claim with Form 1 attached. Claim builder · Deadline checker

  3. The payment schedule

    The payer checks the claim against section 20, works out the serve-by date, and answers with a schedule that has every section 21 item. Received-claim check · Schedule builder

  4. Payment and retention

    Payments and retention go into the project file against the claim they belong to, with the date of each retention report. Retention calculator · Payments

  5. Registers and reports

    Every sheet of the project workbook takes its tool's CSV. The reports read the project file and list the gaps. Project workbook · Reports

What joins what

The files