Received a payment claim? Answer it in time.

For project managers, contract administrators and head contractors. Check what the claim contains, work out the date your payment schedule is due, and build the schedule, all in your browser.

Runs on your device. Information, not legal advice.Nothing you type is sent anywhere or stored, and there are no cookies. This page sets out what the Construction Contracts Act 2002 says. It doesn't decide whether a claim is valid: that's a legal question. If you need advice, talk to a lawyer.

What the claim contains

Tick each item you can find in the claim you received. Section 20 of the Act sets out what a payment claim must contain and what must go with it.

What the Act requires of you, in short

The full detail, section by section: Received a payment claim: what the Act requires of you.

Want your schedule checked before it goes?

Schedule Check $195 (plus GST if applicable): the section 21 contents, the serve-by date, and every reason against the claim and your contract. Invoiced after delivery, due on the 20th of the month after the invoice.

Order a Schedule Check

Where the rules come from (checked 1 Nov 2026)

  • Claim contents: Construction Contracts Act 2002, s20(2)(a) to (f). What must go with it: s20(3) and (4), and Form 1 in Schedule 1 of the Construction Contracts Regulations 2003.
  • Payment schedule: s21(1) to (3). Time and liability: s22. Not paying: s23(1) and (2), s24(1) and (2). Suspension: s24A(1).
  • Read word for word on legislation.govt.nz (Act version as at 5 October 2023, the latest). Many contracts set their own periods and procedures: check yours.