Work out the retention held to date and on this claim from your contract's rates and cap, and when the next retention report is due.
Runs on your device. Information, not legal advice.Nothing you type is sent anywhere or stored, and there are no cookies. The Construction Contracts Act sets no retention rate: the rates and cap come from your contract.
What the Act asks of whoever holds retention money
These rules apply to retention under a commercial construction contract (where no party is a residential occupier), for contracts entered into, or renewed, from 31 March 2017. Read the retention money guide for more.
Construction Contracts Act 2002, subpart 2A (ss 18A to 18Q), s5 "commercial construction contract", s11A(3); legislation.govt.nz, version as at 5 October 2023, checked 1 Nov 2026.